Program Control, Cost, And Schedule

Program Control, Cost, And Schedule
Program Control, Cost, And Schedule

The Integrated Master Plan (IMP) is an event-driven plan that describes the events, significant accomplishments, and accomplishment criteria needed to complete the tasks described in the Contract Work Breakdown Structure (CWBS) dictionary, the Request for Proposal (RFP), and the Statement of Work (SOW) for a particular program.

Typical program events include:

  • Kickoff Meeting
  • System Requirements Review (SRR)
  • Preliminary Design Review (PDR)
  • Critical Design Review (CDR)
  • Test Readiness Review (TRR)
  • Production Readiness Review (PRR)
  • Engineering Development Hardware Deliveries
  • Production Hardware Deliveries

Partnering to Reduce Risk and Accelerate Development

This white paper shows that when system integrators partner with a trusted and proven solution vendor, they are freed from the time commitment and burden of trying to complete every development stage themselves. As a result, they are in a better position to keep projects on spec, on budget and on time.

Each defined event represents the initiation or conclusion of an interval of major program activity. These events are also major decision-points in assessing the maturity of the product development and have specific accomplishments that must be achieved. The events defined cover the entire program from contract award to final hardware acceptance and delivery.

The Program Team develops an Integrated Master Schedule (IMS) which shows all of the detailed tasks required to execute the project. The IMS is tied to the SOW, WBS, and IMP.

Unlike the event-based IMP, the time-based IMS uses a detailed schedule to demonstrate how work efforts will support tasks and events. The IMS is produced based on the IMP. In conjunction with the IMP, the IMS further helps the Program Manager understand the links and interrelationships among the various tasks and teams. Critical path analysis is performed on a monthly basis as part of the program management process. The IMS captures all of the baseline scope of work.

All tasks within the IMS are allocated to a specific Control Account Manager (CAM) or Technical Lead, who has full responsibility, authority, and accountability for completion. CAMs and Technical Leads are assigned to the program to ensure that adequate resources have been assigned to the teams and to ensure schedule performance.

Program Management Capabilities

Dedicated Program Organization  
Dedicated Program Organization

This cross-functional group provides close management of all project activities and agile decision making.

Integral Risk Management  
Integral Risk Management

Proactive risk management provides insights into the program development process and all associated risks, including technical, schedule, and cost risks.

Data Items  
Data Items

We have the expert knowledge to generate all of the data items required for large defense and aerospace programs.

Earned Value Management System  
Earned Value Management System

The EVMS system uses the Integrated Master Plan (IMP) and Integrated Master Schedule (IMS) as its foundation.

Flight Test Program Management  
Flight Test Program Management

Curtiss-Wright has a rigorous project management methodology in place, called ‘Project Path,' to ensure that every project is delivered on time and within budget.

Program Control, Cost, And Schedule  
Program Control, Cost, And Schedule

The Integrated Master Plan includes the events, accomplishments, and criteria needed to complete the tasks in the Work Breakdown, the RFP, and the SOW.

Contract Mandated Reporting  
Contract Mandated Reporting

The Program Managers employ industry-standard management and reporting processes that cover the requirements of a broad segment of its customers.